Which of the following states comes after the 'Implement' state in the Change Management lifecycle?

Study for the IT Service Management (ITSM) Fundamentals Test. Prepare with flashcards and multiple choice questions, each question includes detailed explanations. Get ready for success!

In the Change Management lifecycle, the state that directly follows the 'Implement' state is 'Review.' After a change has been implemented, it is critical to assess whether the change has achieved its intended objectives and to identify any issues that may have arisen during the implementation process. The Review phase involves evaluating the change's performance and confirming that it has been successfully integrated into the environment. This step is essential for understanding the impact of changes and for documenting lessons learned, which can inform future change management practices.

Other states, such as Canceled, Authorize, and Closed, do not occur immediately following the Implement phase. Canceled pertains to changes that were terminated before implementation, Authorize occurs earlier in the process when a change is evaluated and approved before implementation, and Closed represents a final state where all activities and documentation related to the change have been completed after the review process. Therefore, 'Review' is the appropriate and logical transition following the implementation of a change.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy